Archway Early Years Centre
Case Study #
01
Architect:
Kay Hartmann
Heating System:
Main Contractor:
Kier Services
Load Bearing Surface:
Category of Building:
Commercial
Construction ID:
Between Battens / IDEAL ECO
Timber Direct
ECO-60G

18mm ply laid on Fermacell honeycomb acoustic system to provide level and stable substrate for heating system.

Ply layer cleaned and taped up in preparation for heating.

IDEAL panels installed on low density polystyrene panels to ensure aluminium spreader plates are in contact with timber floor above.

Jupiter system and Junckers system installed simultaneously to ensure seamless integration.

Junckers solid oak boards secret nailed into battens.