Construction ID - NEO19-30










Carpet / tile / timber / laminates / synthetics
Liquid anhydrite screed
System IDEAL NEO19 240 kPa

UDL
2.0 kN/m²

Anhydrite screed
Construction height
System foil
JUPITER IDEAL NEO 19
Floor finish
Perimeter insulation
Moisture barrier (if required)
19mm
35mm
Perimeter support batten (optional)
54mm
Technical Data
Construction suitable for rooms with restricted ceiling height
Construction height
mm
54
Height excluding floor finish
Mass
kg/m²
~70
Mass excluding floor finish
Thermal resistance, R-value
m²K/W
0.51
.zip includes:
NBS Spec
.DWG
Uniform Distributed Load (UDL)
Point load (≥ 20cm²)
Impact sound reduction
Area of application
For refurbishment areas with restricted ceiling where minimum insulation requirements are not required
Additional information
kN/m²
2.0
kN
1.5
dB
-
Construction suitable for rooms with restricted ceiling height but does not comply with the minimum insulation level required on intermediate floors.
Should only be used in refurbishment scenarios.
Substrate must be solid, level and flat so that the heating elements can lie flat. Tolerance required as per Surface Regularity 1. (+/- 3mm over 2m)
Curing time for light foot traffic: 1-2 days
Drying time at 20°C and 65% RH: 1 day/mm up to 40mm then 2 days/mm.