1. Heating elements can be fixed to walls using PU rapid installation foam. Alternatively elements can be fixed with screws.

​​

2. Begin installing according to plans at room edge

​​

3. Install elements horizontally and ensure that warm flow into the system begins at the bottom.

​​

4. Snap panels to size.

​​

5. Areas around edges can be filled in using blank insulation.

​​

6. Bring the return water feed back down to connection point using individual strips of Central Zone panels or Edge Zone panels.

​​

7. Specific pipe channels can be formed using the hot wire cutter. Ensure that when forming bends that the curvature is not too tight.
 

8. Clip the pipes into the channels

​​

9. If pipe work needs to be joined, always connect on straight runs and note in pipe bends.

​​

10. Finish with 12.5mm plaster boards. Joins between boards should be filled with flexible filler to allow some expansion / contraction movement.

'no need to screed...'

  • White Facebook Icon
  • White Twitter Icon
  • White Instagram Icon

@JupiterUFH

Jupiter Heating Systems Ltd. 2018 | Unit 1, The Barns, Pennypot Lane, Chobham, Woking, Surrey, United Kingdom, GU24 8DJ

Company No. 05273967 | VAT No. GB 849 3471 91 | Registered in the United Kingdom| Terms of Use | Privacy